Issue with Due Date's in Nifty Task Creation not working

Status: Closed · Asked by RoCrow on · 0 views

RoCrow — Question ·
Task History ID: IjU3NmMwNTZiMDYzMjA0MzY1MjZlNTUzMDUxMzA1MTZiNTQzMiI_3D_pc

I've got a workflow that has a Date/Time formatter step:

That Response is being mapped to the Due Date field in a Nifty > Create Task action:


Unfortunately, that's not working; in Nifty I get a task due date of a couple of days from now instead.

I'm guessing it is an issue with the time format going into Nifty, but I can't for the life of me work out how to fix it.

Please help!

Pabblymember11 — Reply ·

Hey @RoCrow

I've adjusted the input format for the 'Modify Current Date Action' step to match the desired format indicated in the help text. I suggest you try again with the correct due date. Hopefully, this resolves your issue.

Back to all forum threads · Log in to reply