Hey Guys, how do you add +3 days for Perfex CRM from the start date?
Second question, can I use =Now() for the task start date? I tried, but it didn't work; maybe it should be used with a different variable?
Pls guide. Many thanks
Hey @amir
how do you add +3 days for Perfex CRM from the start date?
You can use "Date/Time Formatter by Pabbly: Add/Subtract Time" to add the date time to your desired date.

Second question, can I use =Now() for the task start date? I tried, but it didn't work; maybe it should be used with a different variable?
Yes, you can. Please check the following screenshot for your query.