Task Related Question

Status
Not open for further replies.

zest83

Member
Workflow: https://connect.pabbly.com/workflow/mapping/IjM1MTM0OSI_3D

Google Sheet: Suppose there are 100 rows with Birthday dates & different timings

Now, today being 29th April, there are 15 Birthday messages to be sent and the rest of them are for later dates & timings as defined on the Google Sheet.

If the total sheet has approx 100 different birthday dates & timings
How many tasks are being consumed by the Workflow on the second step "Google Sheet - Get Row" on DAILY BASIS?


Every day the scheduler is running at UTC 1.30

So are 100 Tasks being consumed everyday by the google sheet trigger (second step) in this current workflow
OR
is it being counted as 1 Task OR is it being counted as 15 tasks (number of birthday messages (pre-defined) to be sent today!

I hope I am being clear on the question
 
Last edited:

Supreme

Well-known member
Staff member
Hey @zest83

As per your current workflow, let's say if you are having 3 people having a birthday on the same day it will take 7 tasks.

2022-04-29_17h24_55.png
 

Pabbly

Administrator
Staff member
Check this task History ID -
Task ID - IjEzNjkxOTIzMyI_3D executed at Apr 29, 2022 09:30:07


1651292215118.png



1651292229349.png
 