Perfex CRM - Add Task > =Now() and Due Date

amir

Member
Hey Guys, how do you add +3 days for Perfex CRM from the start date?

Second question, can I use =Now() for the task start date? I tried, but it didn't work; maybe it should be used with a different variable?

Pls guide. Many thanks
 
P

Pabblymember11

Guest
Hey @amir

how do you add +3 days for Perfex CRM from the start date?

You can use "Date/Time Formatter by Pabbly: Add/Subtract Time" to add the date time to your desired date.

2022-04-25_17h01_15.png

Second question, can I use =Now() for the task start date? I tried, but it didn't work; maybe it should be used with a different variable?
Yes, you can. Please check the following screenshot for your query.

1650886169933.png
 