• Instructions to Ask a Question

    Click on the "Ask a Question" button and select the application for which you would like to ask questions.

    We have 5 different products namely - Pabbly Connect, Pabbly Subscription Billing, Pabbly Email Marketing, Pabbly Form Builder, Pabbly Email Verification.

    The turnaround time is 24 hrs (Business Hours - 10.00 AM to 6.00 PM IST, Except Saturday and Sunday). So your kind patience will be highly appreciated!

    🚀🚀Exclusive Discount Offer

    Just in case you're looking for any ongoing offers on Pabbly, you can check the one-time offers listed below. You just need to pay once and use the application forever -
     

    🔥 Pabbly Connect One Time Plan for $249 (🏆Lifetime Access) -  View offer 

    🔥 Pabbly Subscription Billing One Time Plan for $249 (🏆Lifetime Access) - View offer

pinterest autoMATION

Umer003

Member
I am facing an issue with processing multiple rows from Google Sheets in Pabbly Connect. My goal is to send data row by row with a delay between each row to prevent multiple parallel tasks from triggering at the same time. Below is my setup and the problem I am encountering:

My Current Setup:

  1. Trigger: Google Sheets – "New or Updated Spreadsheet Row" (Auto Send on Schedule).
  2. Filter: Only process rows where the "Posted Date" column is empty.
  3. Action: Send the row’s data to Pinterest for pinning.
  4. Delay: I added a delay of 30 minutes using "Delay (Pabbly)".
  5. Update Google Sheets: Once processed, update the "Posted Date" column to mark the row as completed.

The Problem:

  • If I add 50 rows at once, Pabbly triggers 50 parallel tasks at the same time, even though I have added a 30-minute delay.
  • This causes all 50 pins to be scheduled for posting at the same time after the delay ends instead of processing them one by one with a gap of 30 minutes each.
  • I need a way to process only one row at a time, wait 30 minutes, and then move to the next row instead of processing all rows at once.

What I Need:

  • A way to process rows sequentially, not in parallel.
  • A solution where one row is processed at a time, and the next row only starts after the previous one is completed and delayed.
  • Any possible workaround using Google Sheets, API triggers, or Pabbly's built-in tools to achieve this functionality.
Could you please guide me on how to achieve this in Pabbly? Your assistance would be greatly appreciated.
 

Preeti Paryani

Moderator
Staff member
Pro Member
Hello @Umer003,

Could you please provide us with the workflow URL where you are trying to achieve this use case? This will allow us to better assist you.
 